America's Grid Bottleneck, Explained: Why the Transmission Half of U.S. Permitting Reform Is the Part Almost Nobody Argues With

When Congress takes up the bipartisan permitting package next month, the loudest disputes will concern pipelines, environmental review and presidential overrides — not wires. The transmission chapter is the exception, because it adds capacity, cuts congestion costs and unlocks projects already stuck in review queues while taking something away from almost no one inside the coalition that assembled around it.

That narrow agreement is worth decoding even for readers who do not follow energy policy. A podcast conversation turned it into a wider lesson: how monopoly utilities actually make decisions, how American transmission planning fragmented, and why the physical grid, rather than the model or the chip, is the constraint most likely to slow the AI build-out. What follows covers the mechanics, the politics, a comparison table, four misconceptions, a reader checklist and the questions people keep asking.

What is the bill, and how did the story break?

On Thursday, October 29, Robinson Meyer opened a Shift Key episode by framing the biggest story in U.S. energy policy — setting aside the midterm campaign — as the fact that Congress will consider bipartisan permitting reform next month. The package, the Bipartisan American Affordability and Jobs Act, was advanced in September by four senators. Coverage on Heatmap, on Instagram Reels and across social feeds had already shown how divisive the full document is, and the episode itself travels on Apple Podcasts, Spotify, Amazon and YouTube.

Why is the grid chapter the one nobody attacks?

The bill would encourage power-grid expansion, change environmental review laws, make clean energy and pipelines easier to build, and make it harder for presidents to revoke some energy permits. Environmentalists, climate activists and clean-energy advocates have argued over that combination ever since the text appeared, yet most participants concede the electricity section is good. The Natural Resources Defense Council listed it among the bill's "green flags." John Podesta, the former Biden climate advisor, called it "pretty strong" and suggested it could be worth passing if negotiators addressed his other criticisms.

Meyer offered a meta-point that matters for anyone who consumes energy news: journalists reach for conflict because disagreement is a quick way to test contested claims, and that habit drains attention from questions where the evidence points one way. The grid chapter lives in that blind spot.

Who is David Pomerantz, and what does his shop track?

To dig into the uncontested section, Meyer spoke with David Pomerantz, executive director of the Energy and Policy Institute, a watchdog and research group that investigates fossil fuel and monopoly utility lobbying. He has been at the institute for more than 10 years, after spending eight years at Greenpeace and rising to senior climate campaigner. Meyer calls him Dave; the host, Robinson, is the founding executive editor of Heatmap News.

Pomerantz describes EPI as a utility watchdog that mixes investigative work, analysis and communications. Its central task is documenting the harms monopoly utility companies pose to ratepayers and to the transition from fossil fuels to clean energy. Most colleagues are motivated by hastening that transition, but during the last decade his exposure to utility organization and incentives broadened the agenda past utility reform for decarbonization, to how utilities behave toward customers and what can be done about it.

Why did electricity policy stop being only a climate issue?

Meyer observed a familiar pattern: people enter a policy field to cut emissions and then discover deep institutional problems. Pomerantz said he got into this work a little over a decade ago, when the climate community already understood the two-part equation — move the electric sector to clean sources, then electrify everything else practical. Electric utilities sit at the center of that plan, and Meyer added the two parts can run in parallel, since more electric vehicles can be locked in even if short-term power comes from natural gas.

What Pomerantz found is that electricity policy is also good-government policy: campaign finance, concentration of economic power, and cost spillovers, because electricity is a base input for enormous parts of the economy. Recent numbers sharpen that framing. U.S. electricity consumption is projected to rise from a record 4,195 billion kilowatt-hours in 2025 to 4,270 billion in 2026 and 4,349 billion in 2027, per the federal forecasts reported by Reuters — sustained growth after roughly two decades of near-flat demand. Meanwhile Lawrence Berkeley National Laboratory counted roughly 8,200 projects, 1,312 GW of generation and about 749 GW of storage, still seeking grid connection at the end of 2025; projects that reached operation in 2025 had spent an average of eight years in that queue.

Are all electric utilities the same animal?

Asked whether utilities support expansion and decarbonization, or focus on building infrastructure that customers pay for rather than kilowatt-hour growth, Pomerantz answered first that they are not all the same. About two-thirds of America is served by investor-owned electric utilities, corporations owned by investors on Wall Street. The other third is split among public-power forms, including cooperative utilities mostly in rural America and municipal utilities. Even within the investor-owned camp, incentives vary: some companies only sell and distribute electricity, while others also own gas utilities, a pattern that became more common through mergers and acquisitions over the last couple of decades.

Berkshire Hathaway Energy is the sharpest illustration. Berkshire Hathaway, their pipeline group, runs about 20,000 miles of pipe and moved about 15% of the gas consumed in the U.S. in 2024, and the company also owns a majority stake in the LNG terminal Cove Point. Because of that structure, people running electric utilities may be relatively positive about electrification, while people running gas pipelines may not be.

If not carbon, what are utilities really optimizing for?

Pomerantz's read is that most electric utilities are relatively positively inclined toward electrification and mixed on decarbonization — and that people on both sides of climate politics overindex on decarbonization as the defining principle of utility decisions. The most valuable commodity for a utility, he argued, is its monopoly. That leads some utilities in blue states to accept policies that speed the renewable transition while seeking a retrenchment or reification of their franchise: "Yeah, we can dance with decarbonization a little bit, but we want to increase our ownership share of that new clean energy system of assets that we're going to build." He described that tradeoff as having already happened in states with powerful utilities and policymakers who want climate policy without fighting them.

Where did the franchise monopoly come from?

Meyer described the monopoly as a rare corporate right in American law, rooted in the observation that the electricity grid is a natural monopoly: society generally prefers one provider of wires to homes to avoid duplicative infrastructure. That arrangement dates from when distributed electricity was new in the early 20th century, when entrepreneurs raced to string wires and light homes, and he recalled stories from that period in which competing companies strung so much wire in parts of New York City that the sky could be obscured. His formulation: "In this geographic area, only one company can provide electricity service. No other company can do it." Such rights exist for water, electricity and natural gas distribution.

Pomerantz noted that such franchises are very rare in the economy, and pointed to an antitrust debate over whether the natural monopoly rationale still applies. If scale once made one company cheaper, today the defensible monopoly may cover a much smaller part of the electricity value chain, leaving generation, transmission, billing and customer relationships open to competition, which has been introduced in different parts of the country, often with good effect.

What does the bill actually change about transmission?

Meyer said the bill's biggest effect on the power grid may be its transmission provisions, a topic he has covered over the past several years. Pomerantz called the text ambitious in reforming how transmission is planned, permitted, paid for and controlled. For long, high-voltage lines that connect regions and are critical for the energy transition, and also important for cost and reliability, America is building very few regional or interregional lines; construction has basically ground to a halt. The National Conference of State Legislatures notes that once a new line is planned, siting, permitting and building it can take over a decade.

One centerpiece is permitting. Currently, a long line crossing multiple states must be permitted by each state it crosses. The bill would let federal regulators step in and approve a line if one state says no or takes too long and the regulators find it benefits the public; they cannot do it capriciously. For lines of 345 KV or more, the bill would allow parallel filing at FERC while the line also seeks state permission, a mechanic the Congressional Research Service summarizes in its bill overview. The federal lever itself is not new: FERC's backstop siting authority comes from Section 216 of the Federal Power Act, created by the Energy Policy Act of 2005, yet it has rarely been workable in practice, as the commission's own explainer makes clear.

Planning is the second lever. Different parts of the country have different transmission organizations, including RTOs or regional transmission organizations: PJM, which covers the mid-Atlantic states and the eastern part of the Midwest, and MISO, which extends through more Great Plains-like parts of the Midwest. They plan transmission differently, which would not be the design if starting from scratch. Regional transmission organizations did not exist until reforms that started in the late 1990s; for the 20th century, utilities largely decided on their own whether a transmission line was needed. Pomerantz calls the country's position an incomplete journey toward moving transmission control from individual utility companies into the public sphere. BAAJA would advance consolidated planning, getting the country's grid regions to plan in congruent ways, and would attack the interregional problem — lines crossing between regions, such as from PJM to MISO, are basically not being built.

Before and after, at a glance

DimensionPractice todayIf the BAAJA grid chapter passes
Who can approve a multi-state lineEvery state the line crosses must permit itFederal regulators may approve if one state says no or stalls, subject to a public-benefit finding
Filing path for large linesState process first, sequentiallyLines of 345 KV or more can file at FERC in parallel with the state
Planning geographyPJM, MISO and other regions plan on their own rulesConsolidated, congruent planning across regions, plus interregional lines
Typical delivery clockRoughly a decade to site, permit and build (NCSL); eight years in some interconnection queues (LBNL)Compressed approval timelines and narrower judicial remedies, with litigation still likely
Utility incentiveRate-base growth inside a protected franchiseMore assets to own — which is why many utilities do not oppose the grid text

Four misconceptions worth dropping

  • "Permitting reform means the environment loses." The grid chapter's strongest supporters include environmental groups; the Natural Resources Defense Council treated transmission as a positive marker, because renewable build-out is transmission-limited, not enthusiasm-limited.
  • "The U.S. simply does not have enough power." The queue data suggest a delivery problem as much as a generation problem: 1,312 GW of generation is waiting on study and connection, not on interest.
  • "Utilities are one uniform lobby." Two ownership worlds — investor-owned and public power — plus companies that hold both electric and gas assets, produce genuinely different positions on electrification.
  • "Federal backstop authority was invented by this bill." Section 216 dates to 2005; the dispute is over making it usable, not creating it.

A five-question checklist before you trust a grid headline

  1. Is the writer separating the transmission chapter from the environmental-review and pipeline chapters, or treating the package as one object?
  2. Does the analysis name the utility type involved — investor-owned, cooperative or municipal — since incentives differ by ownership?
  3. Is there a line, a queue and a voltage (345 KV or more) attached to the claim, or only adjectives about "speed"?
  4. Who pays: does the piece address cost allocation, not just construction?
  5. Is there a statement about enforceability — what happens when a regulator "cannot do it capriciously" and a permit is challenged in court?

Frequently asked questions

Why would climate advocates back a bill that also helps pipelines?

Because the arithmetic of decarbonization is transmission-bound: cheap wind, solar and storage cannot reach load without lines. That is why figures such as John Podesta described the grid section as "pretty strong" while continuing to press separate objections elsewhere in the package.

Does agreement on the grid chapter mean the bill will pass?

No. Consensus on one chapter lowers the cost of negotiating, but the contested items — environmental review timelines, limits on judicial remedies, presidential permit revocation — are what historically stall this category of legislation. Treat the grid chapter as the anchor that keeps a deal possible, not as proof of a deal.

Will states lose control of siting?

Partially and conditionally. States remain the first-instance permitting authority; the federal role is a backstop triggered by a refusal or delay plus a public-interest finding. The practical question is how often FERC will use authority that has existed since 2005 but has seldom been workable.

What should an ordinary reader expect at home?

Nothing immediate. Transmission additions move wholesale prices and reliability gradually, over years, and the first visible effect would be faster connection for projects already in the queue rather than a bill that changes next month.

Trend judgment: three things to watch

This section is analysis, not reporting. First, watch whether the grid chapter stays intact: reform coalitions usually survive by keeping their consensus core unpoisoned, and both the Natural Resources Defense Council and figures around the Biden climate team have signalled that this section is worth defending even if other parts are renegotiated. Second, watch use, not enactment — a backstop authority that is never invoked changes nothing, and the first attempts to invoke it will be litigated. Third, watch the physical supply chain behind the paperwork: transformers, high-voltage cable, conductors and skilled crews set the floor on delivery time, which is why the AI build-out is ultimately measured in sockets, switchyards and transmission corridors rather than in chips.

Sources and further reading

  • Congressional Research Service, overview of the Bipartisan American Affordability and Jobs Act of 2026 — https://www.congress.gov/crs-product/IN12746
  • FERC, explainer on siting interstate electric transmission facilities (Section 216 backstop authority) — https://www.ferc.gov/explainer-siting-interstate-electric-transmission-facilities
  • Lawrence Berkeley National Laboratory, "Queued Up" interconnection queue research — https://emp.lbl.gov/queues
  • Reuters on federal forecasts for U.S. electricity consumption in 2026 and 2027 — https://www.reuters.com/business/energy/us-power-use-beat-record-highs-2026-2027-ai-use-surges-eia-says-2026-09-09/
  • National Conference of State Legislatures, electric transmission and interconnection queue brief — https://www.ncsl.org/energy/electric-transmission-interconnection-queues
  • Bipartisan Policy Center explainer on the affordability provisions of BAAJA — https://bipartisanpolicy.org/explainer/explaining-the-affordability-in-the-bipartisan-american-affordability-and-jobs-act/
Brand logo

IT Insights

Cloud & Infrastructure Practice Media for Enterprise Technology Decision-Makers

Cloud ComputingSecuritySoftware DevelopmentAI ApplicationsStartupsGeneralAI Data News GlobalAbout Us

© 2026 IT Insights.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.