By James Hartley — ItInsightsWorld, General desk.
Short answer: the AI build-out in the U.S. is running on a two-part workaround. Developers bolt gas turbines to the back of a data center to beat the clock on grid access, then bolt lithium-ion batteries to the front of those turbines to make the whole arrangement survivable — technically, financially and politically. A battery microgrid outside Reno, Nevada is the cleanest worked example of that pattern, and it explains the electricity bills, the permitting fights and the neighborhood deals now spreading across the country.
The conclusion first: the Reno project is not a pilot or a press release. It is a functioning power stack that a recycler turned storage supplier assembled in roughly the time it takes a standard grid-interconnection application to move through its first review cycle.
Redwood Materials — a Nevada battery-recycling and cathode company — put a reported 12 MW / 63 MWh microgrid to work at a data center campus in Sparks, adjacent to Reno, combining a solar array with more than 700 retired electric-vehicle battery packs given a second life as stationary storage, as Canary Media first detailed in July 2025 and as the company describes in its own project note. Batteries are shown powering a data center near Reno, Nevada in an image credited to Redwood Materials.
Three things make the case instructive. First, the storage did not replace generation; it made the generation and the solar usable together, smoothing the violent up-and-down load curve of GPU training runs. Second, the packs were second-life rather than freshly manufactured, which shortened procurement in a market where buyers queue for new containers. Third — and this is the part most coverage skips — the site reached power months before a comparable grid-connected build could have, which is precisely the currency AI developers are spending on.
The electricity load created by data centers is so heavy that large installations may require regulator approval before they can connect to the grid. Rather than wait for that clearance, technology firms eager to construct A.I. infrastructure frequently place gas generators on site.
By one estimate, more than 100 gigawatts of onsite gas power, comparable to 100 large gas power plants, is planned for data centers across the U.S. That number starts to make sense once you look at the queue rather than the turbine. American Action Forum, summarising federal and grid-operator filings, notes that a large load of 200 MW and above typically waits at least five years to connect; grid operators have faced federal orders aimed at shortening that clock.
Across the U.S., companies in the technology sector have provoked criticism for powering large new data centers with polluting gas generators. Energy industry data nevertheless shows that, beyond expanding natural gas, firms are adding very large amounts of battery storage.
To use those gas generators to their fullest, certain companies are installing large lithium-ion batteries next to them, according to a new report from the Solar Energy Industries Association and Benchmark Mineral Intelligence. Batteries are also being used together with renewable energy.
That report finds data centers were responsible for 5 of the nearly 31 gigawatt-hours of battery capacity installed nationally in the first half of this year. It further states they represented 75 percent of the capacity installed at commercial or industrial sites. Analysts expect data center demand for batteries to grow fivefold by the end of this decade.
The economics help explain the curve. BloombergNEF's 2025 price survey put the average pack price for stationary storage at $70 per kilowatt-hour, roughly 45 percent below 2024 — the steepest fall of any battery segment. Cheap enough that a buffer which keeps a gas plant running flat instead of cycling, and which trims peak-demand charges, now pays for itself inside a normal equipment lease term. The same Solar Energy Industries Association and Benchmark Mineral Intelligence outlook line has been revised upward repeatedly this year precisely because hyperscale campuses keep adding storage that utilities did not forecast.
The Memphis build-out offers the same plot with different props. Reporting by Data Center Dynamics in May 2025 counted 168 Tesla Megapack units installed for an AI supercomputer campus there, deployed alongside dozens of mobile gas turbines while substation work continued — a configuration later expanded, according to subsequent site reporting.
Read as a template rather than a headline, the sequence is: energise on turbines, buffer with containers, hand the turbines a backup role once utility capacity arrives. That is the mechanism that lets a campus train models in year one instead of year six, and it is why batteries and gas are growing together rather than competing.
In some localities, residential battery adoption is also being driven by the A.I. expansion, since data centers can earn grid-connection permission by paying for batteries in surrounding homes. These arrangements have owners agree to release battery power to the grid to meet sudden demand peaks. According to analysts, objections to the data center boom could encourage firms to finance additional residential battery projects.
This is not a new instrument wearing an AI label. Utility Dive's reporting on residential demand response describes the same basic contract: a household accepts a utility or sponsor-financed battery, the utility gets dispatch rights during peak hours, and the customer keeps backup power. Connecticut's Green Bank-supported statewide battery program and Alliant Energy's "Smart Hours" payments in Wisconsin are older, public examples of the mechanism that data center financiers are now copying.
Similar approaches are being considered by some firms that want to supply data centers while offering rooftop solar to neighboring households or funding home weatherization to reduce electricity needs for heating and cooling.
New polling from the Yale Program on Climate Change Communication finds that 73 percent of Americans support requiring new data centers to offset their electricity use by installing rooftop solar or weatherizing nearby homes.
In a recent Yale Environment 360 interview, former Energy Department official Jigar Shah suggested that weatherizing homes could ultimately cost technology firms less than installing gas turbines on site, even before considering public opinion. "At the end of the day, these [companies] need public permission," Shah said. He added, "Figuring out how to gain that permission I think is also something the data centers have to solve."
| Route | Problem it solves | Realistic lead time | Where it falls short |
|---|---|---|---|
| On-site gas turbines | Skips the interconnection queue; gets silicon energised | Months, if air and noise permits clear | Local opposition, fuel-price exposure, emissions criticism |
| On-site or second-life batteries | Buffers GPU load swings, firms up turbines and solar, cuts peak charges | Months; supply-queue risk on new cells | Four-to-eight-hour buffering, not a season of power |
| Community spending (home batteries, rooftop solar, weatherization) | Reduces net new demand and buys local consent | One to three years to build at scale | Hard to verify savings; needs regulator sign-off |
Because the plant is only half the job. GPU training loads surge and collapse second by second, and turbines ramp slowly and wear out doing it. The battery absorbs the spikes, so the turbine runs at a steady output and the campus can keep a contract it signed months earlier.
No, but the U.S. shows it most sharply because grid access is fragmented across operators and states, so waiting is long and local consent is contestable. The International Energy Agency projects that data centres account for nearly half of U.S. electricity demand growth through 2030, which is why the workaround is scaling so fast.
The Reno case is the proof of concept: second-life packs, paired with solar, running a live campus load. Degraded cells matter less for stationary duty than for driving, so long as the operator accepts a shorter replacement cycle.
Run one test: who controls dispatch, how often, and what happens to your backup reserve. Programs that pay transparently per kilowatt-hour dispatched and guarantee a minimum reserve are contracts; programs that don't are a subsidy with fine print.
Weatherization and rooftop offsets lower net new demand, which is the cheapest kilowatt available. Deloitte's infrastructure research estimates U.S. AI data center power demand could reach 123 GW by 2035, so offsets shape the growth rate rather than erase it.
What the Nevada microgrid and its Memphis cousin demonstrate is not that clean power beat gas, or that gas beat the grid. It is that time became the scarce input, and that batteries — new, second-life, or installed in somebody else's garage — turned out to be the fastest thing available. For readers, the useful habit is to stop asking how big the next data center will be and start asking how it got power, who paid for the buffer, and what happens to the neighbourhood when the turbines move from bridge to permanent.