By James Hartley · IT Insights · General insights series
Power lines in Tianjin, China. Yucun Tang via Flickr
Two very different failures look almost identical from the outside: a country that has erected enormous amounts of wind and solar yet cannot use all of it. China’s version is curtailment — plant that is built, connected and capable, but switched down by the operator. The American version is the queue — projects that never reach energisation because permission to connect takes years. Both trace back to wires rather than panels, and knowing which failure you are reading about changes the conclusion you should draw from the headline.
Answer in one line: curtailment is the deliberate refusal of electricity that a plant is ready to deliver. Supply and demand must balance second by second, grid-scale storage is still scarce, and solar and wind cannot be switched on at will — so when midday output outruns local load and the lines leaving the region, the control room instructs wind farms to hold back and solar parks to limit their inverters.
That distinction shapes how you should judge the loss. A curtailed megawatt-hour is usually a sale that never happened rather than generated power dumped uselessly: the turbines, the land and the capital are already sunk, but the chance to earn from them is gone. This part is an IT Insights reading of how operators run the system, not a new statistic.
Conclusion first: enough to cover the country’s entire growth in electricity demand. China leads the world in renewable energy, and last year it added more wind and solar capacity than all other nations combined; the build simply ran ahead of the network that has to absorb it. In the first six months of this year China rejected 360 terawatt-hours of clean energy, a volume sufficient to power Mexico for a year, according to a report from Global Energy Monitor and the Centre for Research on Energy and Clean Air. “Had this electricity been absorbed, the additional power supply could have met all demand growth and allowed coal power generation to fall,” the report’s authors wrote.
The trend line matters as much as the total. Global Energy Monitor’s published account of the same estimate describes curtailed wind and solar — counting both reported and unreported volumes — as roughly 49 percent higher than in the equivalent period a year earlier. On that reckoning, 26.1 percent of wind and solar output was rejected in the first half of this year, far above the utilisation percentages that grid companies release themselves.
Two causes, and neither is about the weather. The first is a shortage of transmission lines able to carry abundant clean energy from where it is generated to where it is needed; the second is a policy that guarantees the purchase of electricity from newly built coal plants, which hands fossil generation a protected customer before the wind and the sun have been dispatched.
“Coal capacity is still growing because of legacy approvals and policy protections, even as plants run fewer hours and large volumes of clean electricity go unused,” said Qi Qin, an analyst at the Centre for Research on Energy and Clean Air.
The fix now being funded is the biggest grid-building programme on record. China’s State Grid has outlined about CNY 4 trillion — roughly US$574 billion — of network investment for 2026 to 2030, some 40 percent above the previous five-year plan, together with 15 new ultra-high-voltage lines intended to lift cross-regional transmission capability by around 35 percent, according to Xinhua reporting carried by Enerdata and China Daily. The timing is the catch: money committed for the 2026–2030 window cannot unlock the congestion of 2026.
Short answer: wasted output is the cheaper problem to solve, because the hardware already exists and only rules and wires are missing.
| Decision dimension | China | India | United States | Australia |
|---|---|---|---|---|
| Where the power gets stuck | After construction: the grid refuses output | Mostly after construction, plus tight evening margins | Before construction: projects wait to be approved for connection | At the moment of plenty: midday oversupply and negative prices |
| Signature figure | 360 terawatt-hours turned away in the first six months of this year | 34 gigawatt-hours lost on a single day in March | About 1,312 GW of generation still queued at the end of 2025 | Record 9.1 GW connected in a single financial year |
| Dominant cause | Missing long-distance lines; protected coal offtake | Transmission lag; coal units parked at minimum output for evening peak | Permitting, rights of way, review backlogs | Connection pipeline growing faster than network works |
| Who absorbs the loss | Project owners, through lost sales and lower merchant prices | State discoms, through compensation paid to generators | Developers, through idle capital and expired land options | Owners of wind and solar farms facing paid and unpaid curtailment |
| Main remedy in flight | Ultra-high-voltage corridors and market reform | Transmission augmentation and battery build-out | Interconnection queue reform | Batteries and grid-forming inverter standards |
| Time to relief | Years, but the assets are already built | Years, and the volumes are smaller | A decade or more for large lines | Shorter, because the constraint is connections not distance |
Read across that grid and one pattern stands out. A country that has finished the generation but cannot absorb it needs wires, market rules and flexibility. A country whose projects pile up in administrative queues needs throughput, and that is a slower, less expensive-looking but more corrosive failure. Berkeley Lab’s Queued Up research series counted roughly 8,200 US projects actively seeking grid connection at the end of 2025, representing about 1,312 GW of generation plus some 749 GW of storage, and found that a project completing the process in 2022 had typically spent about five years in line, against three years in 2015. Every year in a queue is capital earning nothing; every terawatt-hour curtailed is revenue that never arrives.
Nations with large renewable fleets also struggle with wasted power. In India, clean power capacity just surpassed fossil fuel capacity for the first time, yet transmission infrastructure has not kept pace. On a single day in March, India wasted 34 gigawatt-hours of clean electricity, enough to power about 5 million homes, according to an analysis from the think tank Ember. The core of the problem, analysts said, “is a growing mismatch between the pace of renewable energy development and the readiness of the transmission infrastructure.”
Ember’s later accounting frames India’s shortfall differently from China’s: curtailed renewable output of roughly 2.1 terawatt-hours in fiscal year 2025–26, equal to about 1.3 percent of the country’s renewable generation, and a companion estimate that some 10 GWh of grid batteries would remove most of it. The diagnosis from Ember’s analysts is that transmission constraints and grid-security actions, rather than soft demand, drive the cuts — which is why battery storage features so prominently in the Indian remedy.
Use this five-point frame instead of reacting to the word “waste”:
Because the two decisions are made by different parties on different clocks. Generation permits can be granted and panels installed within months, while a long-distance line needs years of routing, approval and construction. The gap between those clocks is where curtailment is born.
Rarely. In most reported cases operators ask plants to hold back output, so the energy is never generated in the first place. The waste is economic — a stranded opportunity and a sunk asset — rather than physical.
It raises the cost per delivered unit, because capital is deployed against hours of generation that never occur. That is why independent estimators such as the Centre for Research on Energy and Clean Air count unreported volumes as well as published ones.
China’s is larger by volume by a wide margin, but the United States’ is larger by lost time: roughly 1,312 GW of queued generation at the end of 2025 versus 360 terawatt-hours of refused output in the first six months of this year. One is a stock of unbuilt projects; the other is a flow of unbuilt sales.
Three things with different speed ratings: better forecasting and intraday market rules (months), storage and flexible demand (one to three years), and new long-distance transmission (five to ten years). Analysts who study both markets keep arriving at the same place — the transmission pipeline.
Bottom line for a general reader: the interesting fact here is not that clean electricity is being wasted, but that the constraint has moved from generators to networks — and networks are governed by rules, rights of way and balance sheets, which means they can be reformed as well as built. Corrections, tips and reader questions for IT Insights are welcome at contact@itinsights.com.